19
SEPTEMBER 2009
Status (1)
• No stand-alone
solution economic
• Collective solution needed to
improve economics
- increased reserves base
- more appraisal drilling
- lower project cost
- increased gas
price certainty
• Tormore discovery increased
reserves substantially
• Sufficiently encouraging for
more, dettailed work
Status (2)
• Two cornerstone projects
- Laggan/Tormore +
Rosebank/Lochnagar
• Industry test appetite for
3rd Party investment
• Total have started basic
engineering for Laggan/Tormore
- onshore hub with gas
export to St Fergus
- New pipeline
capacity og 18 million
cm/d. Meets capacity
requets from potential
3rd parties
• Development Plan
submission in early 2010 for
Govenment consideration?
Deep Water Oil & Gas Hub
Deep Water Gas Hub